SSD Modifications
Determination
Mod 12 - Underground Extraction Rates
Mid-Western Regional
Current Status: Determination
Interact with the stages for their names
- SEARs
- Prepare Mod Report
- Exhibition
- Collate Submissions
- Assessment
- Recommendation
- Determination
Attachments & Resources
EA (14)
Response to Submissions (1)
Recommendation (9)
Determination (5)
Submissions
Showing 41 - 46 of 46 submissions
Central West Environment Council
Object
Central West Environment Council
Object
Summer Hill Creek
,
New South Wales
Message
See attachment.
Attachments
Ian & Robyn Moore
Object
Ian & Robyn Moore
Object
Jerry's Plains
,
New South Wales
Message
See attached.
Attachments
judith leslie
Object
judith leslie
Object
Bulga
,
New South Wales
Message
See attachement
Attachments
Alan Leslie
Object
Alan Leslie
Object
Roads and Maritime Services
Comment
Roads and Maritime Services
Comment
Department of Primary Industries
Comment
Department of Primary Industries
Comment
Sydney
,
New South Wales
Message
See attached.
Attachments
Pagination
Project Details
Application Number
MP05_0117-Mod-12
Main Project
MP05_0117
Assessment Type
SSD Modifications
Development Type
Coal Mining
Local Government Areas
Mid-Western Regional
Decision
Approved
Determination Date
Decider
IPC-N
Related Projects
MP05_0117-Mod-1
Determination
SSD Modifications
Mod 1 - Infrastructure Area Layout
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-2
Determination
SSD Modifications
Mod 2 - Preliminary Construction Walk
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-3
Determination
SSD Modifications
Mod 3 - Additional Coal Processing
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-4
Determination
SSD Modifications
Mod 4 - Rail Loop Changes
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-5
Determination
SSD Modifications
Mod 5 - Water Pipeline & Other Changes
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-6
Determination
SSD Modifications
Mod 6 - Coal Rejects Bin
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-7
Determination
SSD Modifications
Mod 7 - Borefield
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-8
Determination
SSD Modifications
Mod 8 - Coal Stockpile
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-9
Determination
SSD Modifications
Mod 9 - Additional Coal Extraction
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-10
Determination
SSD Modifications
Mod 10 - Increase Production Limit
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-11
Determination
SSD Modifications
Mod 11 - Design Refinements
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-12
Determination
SSD Modifications
Mod 12 - Underground Extraction Rates
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-13
Determination
SSD Modifications
Mod 13 - Coal Processing Rates
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-14
Determination
SSD Modifications
Mod 14 - Water Discharges + Coal Extraction
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-15
Determination
SSD Modifications
Moolarben Stage 1 MOD 15 - UG4 Ancillary Works
Locked Bag 2003 Mudgee New South Wales Australia 2850
MP05_0117-Mod-16
Determination
SSD Modifications
Mod 16 - CWO Transmission Line
Locked Bag 2003 Mudgee New South Wales Australia 2850