Skip to main content

State Significant Infrastructure

Determination

Tallawarra B Power Station

Wollongong City

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Assessment
  6. Recommendation
  7. Determination

Construction and operation of a gas turbine power station with a nominal capacity of up to 300-450 megawatts (MW) and ancillary infrastructure and utilisation of existing infrastructure.

Consolidated Approval

Tallawarra B (MOD2) - Consolidated Project Approval

Modifications

Prepare Mod Report

Archive

Application (2)

Project Application.pdf
Preliminary Assessment.pdf

DGRs (1)

Director-General Requirements for the Environmental ...

EA (19)

Appendix D - Greenhouse Gas Assessment.pdf
Appendix B - AirQuality.pdf
Chapter 0 - ToC Certification and Executive summary.pdf
Appendix F - Prelim Hazard Analysis.pdf
Chapter 2 - Statutory Provisions.pdf
Chapter 10 - Conclusion.pdf
Chapter 4 - Stakeholder Consultation.pdf
Chapter 3 - Strategic justification.pdf
Chapter 11 - References.pdf
Chapter 9 - Statement of Commitments.pdf
Chapter 1 - Introduction.pdf
Chapter 8 - Combined Cycle Gas Turbine_Final.pdf
Appendix G - Water Quality Calculations.pdf
Chapter 7 - Open Cycle Gas Turbine_Final.pdf
Appendix E - Noise Assessment_Final.pdf
Chapter 6 - Existing environment.pdf
Appendix C - Plume Rise Assessment.pdf
Chapter 5 - Project Description_Final.pdf
Appendix A - Stakeholder Correspondence.pdf

Response to Submissions (5)

Part 1 Tallawarra Stage B Submissions Report.pdf
Part 2 Submissions Report Closed Cycle Gas Turbine_...
Part 2 Submissions Report Aviation Safety Issues.pdf
Part 2 Submissions Report Closed Cycle Gas Turbine_...
Part 2 Submissions Report Open Cycle Gas Turbine_Pl...

Determination (3)

Director-General's Assessment Report.pdf
Director-General's Assessment Report - Appendix E.pdf
Project Approval.pdf

Approved Documents

Management Plans and Strategies (28)

Traffic Management Plan
Environmental Management Strategy
CEMP Approval
Environmental Management Strategy (Ver 2.4) - Approval
Environmental Management Strategy (Ver 2.4)
Construction Environmental Management Plan (CEMP)
Soil and Water Management Plan
Environmental Management Strategy Approval
Aboriginal Cultural Heritage M P Approval
Flora and Fauna Management Sub-Plan Approval
Noise and Air Quality Management Sub-Plan Approval
Traffic Management Sub-Plan Approval
Waste Management Sub Plan Approval
Soil and Water Management Sub-Plan Approval
Environmental Management Strategy
Aboriginal Cultural Heritage Management Plan
Flora and Fauna Management Sub-Plan
Noise and Air Quality Management Sub-Plan
Traffic Management Sub-Plan
Waste Management Sub Plan
Soil and Water Management Sub-Plan
Vegetation Offset Plan (v2.4) - Approval
Vegetation Offset Plan (v2.4)
Vegetation Offset Plan - Letter to DPIE Dec 2022
Community Consultation Program Approval
Community Consultation Program
Flora & Fauna Management Plan
Noise & Air Quality Management Plan

Reports (8)

2021-09-17 DPIE Letter to EnergyAustralia_Aviation Impact Assessment
2021-09-17 - DPIE Letter to EnergyAustralia - Attachment 2
2021-09-17 - DPIE Letter to EnergyAustralia - Attachment 4
2021-09-17 - DPIE Letter to EnergyAustralia - Attachment 5
2021-09-17 - DPIE Letter to EnergyAustralia - Attachment 6
2021-09-17 - DPIE Letter to EnergyAustralia - Attachment 7
2021-09-17 - DPIE Letter to EnergyAustralia - Attachment 3
2021-09-17 - DPIE Letter to EnergyAustralia - Attachment 1

Independent Reviews and Audits (4)

Independent Audit Report June 2022
1313 Tallawarra Stage B IEA_Audit 2_Final Report
Proponent Response to Audit Findings
Proponent Response to Audit Findings 8 Dec 2022

Other Documents (1)

Environmental Representative Approval

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

18/01/2022

05/04/2022

28/06/2022

25/08/2022

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Project Details

Application Number
MP07_0124
Assessment Type
State Significant Infrastructure
Local Government Areas
Wollongong City
Decision
Approved
Determination Date
Decider
Minister
Last Modified By
MP07_0124-Mod-2
Last Modified On
07/12/2020

Contact Planner

Name
Neville Osborne