Part 5 Activities
Bradfield City Centre Stage 2A Civil Works
Liverpool
The Stage 2A Enabling Works covers a site area of approximately 38 hectares of land within the Bradfield City Centre site, and involves delivery of new roads, streetscape works, civil works and public utilities to be delivered in a staged construction scheduled to be completed by 2026.
Specifically, the proposed Activity consists of the following:
• construction of new roads and associated road infrastructure
• site clearing (including removal of vegetation) and associated earthworks
• provision of service authority utilities within the road corridors
• street landscaping
• drainage and stormwater infrastructure (including temporary stormwater basins)
• stockpiling of excess soil
• construction of temporary haul roads during construction.
The Stage 2A Enabling Works will deliver fully serviced development superlots. This work includes bulk earthworks, civil road works, grading and levels for the site, public utilities, open space, and street landscaping. Completion of these works will