The demolition would proceed as follows:
1. The A-frame building (timber frame cladded with metal sheeting with metal-framed glass
windows)
a. Isolate then disconnect electrical service to main structure
b. Disassemble front verandah along with sponsor signage board
c. Remove windows
d. Disassemble metal sheet cladding
e. Deconstruct all timber substructure
f. Demolish all concrete style concrete pad footing
g. Load all components into mobile waste bin for off-site disposal to licenced waste
facility
2. Weigh-in Station (galvanised metal)
a. Break down structure via bolt attachments noting some element of grinding may be
required
b. Demolish all concrete style concrete pads and supporting structure
c. Load direct onto truck or skip bin for off-site disposal at licenced waste facility.
3. Signage – metal signage to be deconstructed and stored off-site.
4. Clear site of all remaining materials and make good with adjoining environment.