Part 5 Activities

Determined

Jetty Repair (through renewal), St Georges Basin estuary, Island Point Road, St Georges Basin

Shoalhaven

The proposed activity is the repair, through renewal, of an existing jetty within St Georges Basin (the estuary) off Island Point Road, St Georges Basin. This jetty was severely damaged during numerous storm events in 2022.
The proposed activity would comprise:
• site preparation works including the establishment of a temporary construction zone within cleared areas, sediment fencing, barge installation, and container and temporary toilet
installation
• demolition and removal of the existing timber jetty
• replacement with a jetty comprising:
o 32 metres long by 4 metre wide composite fibre (FRP) jetty
o gangway – 8.5 metres long by 1.5 metre wide attached to a floating pontoon
structure – 6 metres long by 4 metres wide for closer access to the water
o associated piles / piers (25) for the jetty and another 2 piles for the floating pontoon
that extend above the 2050 1% AEP flood level
• installation of seating and fishing-rod holders

Review of Environmental Factors (REF) (1)

The approved project is described in the REF, as modified by any associated decision statement (see supporting documents).
Review of Environmental Factors
Review of Environmental Factors REF - Jetty Renewal - St Georges Basin - Island Point Road St Georges Basin
Date : Tue, 03/10/2023 - 15:37

Activity Details

Reference number
P5-2023-123
Proponent(s)
Shoalhaven City Council
Address
2 Island Point Road St Georges Basin 2540
Legislation
TISEPP (State Environmental Planning Policy (Transport & Infrastructure) 2021)
Activity Type
Port, wharf or boating facilities
Decision
Approved
Determination date