Part 5 Activities
Proposed new bridge over Conjola Creek, Murrays Road, Conjola
Shoalhaven
The proposed activity is the construction of a new bridge and associated works. The new bridge would be constructed immediately downstream of the existing, heritage-listed bridge that would be retained as a ruin.
In summary works would involve:
• the protection of the existing, heritage listed bridge
• traffic management
• vegetation removal including 13 trees
• operation of erosion, sediment and pollution controls
• piling
• construction of abutments, headstocks and wingwalls involving.
• installation of scour protection (500mm diameter rock) in front of the abutment and wingwall.
• installation of bridge girders, deck and barriers.
• construction of sealed approaches to the bridge.
Murrays Road, Bendalong Mountain Road and the currently unmaintained road verge connecting the two roads would be made trafficable to allow access to properties on the eastern side of the creek when the cranes are operating this side.
Review of Environmental Factors (REF) (1)
Plans (1)
Supporting Documents (3)
Activity Details
Conjola