CIV > $5M - Private infrastructure and community facilities
Determined
Alterations & Additions to Community Facility - Lauren Jackson Stadium - Stage 1
Southern Regional Planning Panel
Replacement of roof and gutters, demolitionn of grandstand and reconfiguration of courts to allot additional seating. Replace flooring, renovate internal spaces & amenities. Removal of existing tree, replace external cladding with windows on south facade. Upgrade to facade and extend overhang over entrance. Carparking upgrade, landscaping and outdoor enclosure to house fire tanks.
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
PPSSTH-76 FINAL Determinatio & SOR
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
PPSSTH-76 Planning Panels Meeting Declaration Form
Council Assessment Report (2)
Attachments to Council Assessment Report (3)
Other (9)
Cost estimate report
Cost Summary Report
DA Application form
Development Application Form - PAN-57254
Geotechnical report
Soil Report
Other
RPP Report Cover Sheet PPSSTH-76
Other
Final Independent Assessment Report
Other
Final Development Plans for RPP
Other
Attachment 1 to Independent Assessment Report - Draft Developmen
Statement of environmental effects
Statement of Environmental Effects - SEE
Survey plan
Survey Plan
Project Details
DA
number
10.2021.38113.1
Planning panel reference number
PPSSTH-76
Capital investment value
$10,660,000
Project Address
229 North Street East Albury 2640
Lodgement date
Referral date
Local government
Albury City Council
Type of matter
DA
Determination outcome
Approved