Change of use of part of site to a Waste or Resource Transfer Station – Hornsby Community Recycling Centre

Sydney North Planning Panel

The proposed development is for a change of use of part of the site from a Depot to a Waste Management Facility to facilitate the ongoing use of the site as a Community Recycling Centre with an acceptance limit of 2,500 tonnes of waste per annum. The facility will likely handle small quantities of substances classified in the ADG Code

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
PPSSNH-459 Panel Decision

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
PPSSNH-459 Panel declaration forms

Council Assessment Report (1)

Council Assessment Report
SNPP Assessment Report DA 14 2024

Attachments to Council Assessment Report (4)

Attachment to assessment report
DA 14 2024 - Attachment C - Operational Plan of Management
Attachment to assessment report
DA 14 2024 - Attachment B - Architectural Plans
Attachment to assessment report
DA 14 2024 - Attachment A - Draft Conditions
Attachment – recommended conditions of consent
10 July 2024 - Revised - Draft Conditions DA 14 2024

Project Details

DA number
DA/14/2024
Planning panel reference number
PPSSNH-459
Capital investment value
$0
Project Address
4 Chilvers Road Thornleigh 2120
Lodgement date
Referral date
Local government
The Council Of The Shire Of Hornsby
Type of matter
DA
Determination outcome
Approved
Determination Date