Designated Development - Waste Facility
Determined
Change of use for a resource recovery facility. The development is designated development under Schedule 3 of the Environmental Planning & Assessment Regulation 2021
Sydney Western City Planning Panel
Use of Unit 3 in the existing industrial building, for the purpose a Waste Management Facility and Works for the purpose of a Resource Recovery Facility processing up to 4,800 tonnes per annum of organic waste utilising Black Soldier Fly. The development is Designated Development under Schedule 3 of the Environmental Planning & Assessment Regulation 2021
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
Determination & SOR PPSSWC-349 – Fairfield – DA 219.12023 – 132 Newton Road, Wetherill Park
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
Panel Declarations PPSSWC-349
Council Assessment Report (1)
Council Assessment Report
Delegated Town Planning Assessment Report
Attachments to Council Assessment Report (17)
Attachment to assessment report
ATTACHMENT A – Architectural Plans
Attachment to assessment report
ATTACHMENT C – Environmental Impact Statement
Attachment to assessment report
ATTACHMENT F – Air Quality Impact Assessment Report
Attachment to assessment report
ATTACHMENT D – Environmental Management Plan
Attachment to assessment report
ATTACHMENT I – Flood Risk Management Report
Attachment to assessment report
ATTACHMENT J – SEPP 33 Assessment
Attachment to assessment report
ATTACHMENT N – Response to Submissions Report
Attachment to assessment report
ATTACHMENT O – SESL Response to EPA Comments
Attachment to assessment report
ATTACHMENT E – Noise Impact Assessment
Attachment to assessment report
ATTACHMENT H – BCA Compliance Assessment
Attachment to assessment report
ATTACHMENT K – Business Management Plan
Attachment to assessment report
ATTACHMENT G – Odour Response Letter
Attachment to assessment report
ATTACHMENT L – Environment Protection Authority (EPA) General Terms of Approval
Attachment to assessment report
ATTACHMENT B – Fairfield City Wide Development Control Plan 2013 Compliance Table
Attachment to assessment report
ATTACHMENT P – Goterra Response to Fairfield City Council
Attachment to assessment report
ATTACHMENT M – Transport for New South Wales (TfNSW) Agency Advice
Attachment – recommended conditions of consent
ATTACHMENT Q – Draft Conditions of Consent
Other (1)
Record of kick-off briefing
SWCPP Kick off Record of Briefing PPSSWC-349 Fairfield DA 219.1.2023 132 Newton Road Wetherill Park
Project Details
DA
number
DA 219.1/2023
Planning panel reference number
PPSSWC-349
Capital investment value
$903,482
Project Address
132 Newton Road Wetherill Park 2164
Lodgement date
Referral date
Local government
Fairfield City Council
Type of matter
DA
Determination outcome
Approved
Determination Date