CIV > $5M - Private infrastructure and community facilities

Determined

Electricity Generating Works (2 x 5MW Solar Farm) and Associated Infrastructure

Western Regional Planning Panel

Electricity Generating Works (2 x 5MW Solar Farm) and Associated Infrastructure

Determination and Statement of Reasons (1)

Determination and Statement of Reasons
PPSWES-2 Determination SOR 21 Dec 2020

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
PPSWES-2 Panel Declarations 21 Dec 2020

Council Assessment Report (1)

Council Assessment Report
Council Assessment Report & Cover Sheet - WRPP

Attachments to Council Assessment Report (7)

Attachment to assessment report
Attachment 1 - Site Photos
Attachment to assessment report
Attachment 7 - Draft Conditions
Attachment to assessment report
Attachment 6 - Referral Responses
Attachment to assessment report
Attachment 5 - Applicant response to Submissions Round 2
Attachment to assessment report
Attachment 4 - Amended Site Plan and Traffic Assessment - Octobe
Attachment to assessment report
Attachment 3 - Further Information Response
Attachment to assessment report
Attachment 2 - Development Application Documents Lodged

Record of Briefing (1)

Record of Briefing
PPSWES-2 Record of Briefing & Site Visit 4 August 2020

Other (1)

Notice of Panel Meeting
PPSWES-2 Notice of Meeting 21 December 2020

Links (1)

URL
Audio recording public determination meeting 21 December 2020

Meetings

Public determination meeting

Chaired by: Garry Fielding

Project Details

DA number
DA0288/2019
Planning panel reference number
PPSWES-2
Capital investment value
$13,200,000
Project Address
3B Sydney Road Burrundulla 2850
Lodgement date
Referral date
Local government
Mid-Western Regional Council
Type of matter
DA
Legal appeal description
Refusal and Class 1 Appeal
Determination outcome
Refused