Proposal to increase the amount of material currently extracted from approximately 30,000 cubic metres to a maximum of 75,000 cubic metres per annum over the next 4 years (2015-2018). After the initial 4 year period it is envisaged that the quarry will continue to operate at a reduced extraction rate (approximately 20,000 cubic metres) for a total period of 20 years (2035). Extraction of the material will occur over three stages with site rehabilitation to occur at the conclusion of each stage.
Other (1)
Other
Withdrawal letter.pdf
Project Details
DA
number
DA0034/2016
Planning panel reference number
PPS-2015WES013
Capital investment value
$123,942
Project Address
2778 Ulan Road, Cooks Gap
Lodgement date
Referral date
Local government
Mid-Western Regional Council
Type of matter
DA
Determination outcome
Withdrawn
Determination Date