1. Ongoing extraction of quartzose rock within the existing extraction area and a 4.4ha extension of the extraction area, producing up to 230000tpa.
2. Campaign crushing and screening on site using mobile processing equipment. On-site processing as per client requirements.
3. Ongoing transportation of fragmented and crushed rock to the state road for delivery to the Sunnyside Plant and other destinations.
4. Ongoing transportation of material directly to end points of use when not required for processing at Sunnyside Plant.
5. Ongoing backloading of clay and crusher fines from the Sunnyside Plant to the site.
6. Progressive emplacement of overburden and fines within and adjacent to the extraction area.
7. Progressive and final rehabilitation of the site.

Project Details

DA number
2019.101
Planning panel reference number
PPSNTH-13
Capital investment value
$60,000
Project Address
Mt Lindesay Road, Tenterfield Nsw 2372
Lodgement date
Referral date
Local government
Tenterfield Shire Council
Type of matter