Concept DA that meets criteria under the State and Regional Development SEPP
Determined
Proposal for a Concept Master Plan for the Wolumla Estate Project Area and the first stage of development (being Stage 1)
Southern Regional Planning Panel
Proposal for a Concept Master Plan for the Wolumla Estate Project Area and the first stage of development (being Stage 1) comprising:
-Torrens title subdivision to create 170 residential allotments, one (1) allotment for future commercial development, three (3) allotments for water sensitive urban design and/or public open space purposes and one (1) residual allotment for the future stages of development.
- Civil construction works.
- Tree removal and landscaping works
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
Determination Statement of Reasons - PPSSTH-343 (SECURED)
Completed Panel Declaration forms (1)
Completed Panel Declaration forms
PPSSTH-343 - Planning Panels Declarations combined (SECURED)
Council Assessment Report (1)
Council Assessment Report
2023.351 Planning Panel Report
Attachments to Council Assessment Report (17)
Attachment to assessment report
2023.351 ATTACHMENT 3 CONCEPT MASTER PLAN REPORT
Attachment to assessment report
2023.351 ATTACHMENT 5 REVISED ENGINEERING CONCEPT DESIGN FOR CONCEPT MASTERPLAN
Attachment to assessment report
2023.351 ATTACHMENT 6 CIVIL ENGINEERING DRAWINGS STAGE 1
Attachment to assessment report
2023.351 ATTACHMENT 9 TRAFFIC IMPACT STATEMENT
Attachment to assessment report
2023.351 ATTACHMENT 13 EARTHWORKS PLAN STAGE 1
Attachment to assessment report
2023.351 ATTACHMENT 7 FLOOD IMPACT RISK ASSESSMENT REPORT
Attachment to assessment report
2023.351 ATTACHMENT 12 REVISED STORMWATER LANDSCAPE PLAN
Attachment to assessment report
2023.351 ATTACHMENT 10 BIODIVERSITY ASSESSMENT REPORT FINAL
Attachment to assessment report
2023.351 ATTACHMENT 17 DEPT PLANNING AND ENV - WATER GENERAL TERMS OF APPROVAL
Attachment to assessment report
2023.351 ATTACHMENT 11 SEWER MASTERPLAN
Attachment to assessment report
ATTACHMENT 16 HERITAGE NSW GENERAL TERMS OF APPROVAL
Attachment to assessment report
2023.351 ATTACHMENT 14 TRANSPORT FOR NSW COMMENTS
Attachment to assessment report
2023.351 ATTACHMENT 15 RFS GENERAL TERMS OF APPROVAL
Attachment to assessment report
2023.351 ATTACHMENT 8 STORMWATER CATCHMENT PLAN
Attachment to assessment report
2023.351 ATTACHMENT 4 CLAUSE 4.6 VARIATION REQUEST
Attachment to assessment report
2023.351 ATTACHMENT 2 REVISED STATEMENT OF ENVIRONMENTAL EFFECTS
Attachment – recommended conditions of consent
2023.351 AMENDED ATTACHMENT 1 DRAFT CONDITIONS
Record of Briefing (1)
Record of Briefing
PPSSTH-343 - Record of Briefing 16.04.2024
Record of Site Visit (1)
Record of Site Visit
PPSSTH-343 - Record of Site Inspection 23.05.2024
Other (1)
Notice of Panel Meeting
PPSSTH-343 - Notice of Public Meeting 25 August 2026 (register to receive details)
Links (1)
URL
SOUTHERN REGIONAL PLANNING PANEL - Audio Recording - PPSSTH-343 - 25 August 2026
Meetings
Public determination meeting
Chaired by:
Chris Wilson
Project Details
DA
number
2023.351
Planning panel reference number
PPSSTH-343
Capital investment value
$57,540,653
Project Address
22 Mine Lane Wolumla 2550
Lodgement date
Referral date
Local government
Bega Valley Shire Council
Type of matter
DA
Determination outcome
Approved
Determination Date