Snowy 2.0 - Exploratory Works

MOD 1 - Substation and further geotechnical investigations

1. Additional borehole drilling and geophysical surveys;
2. Establishment of a construction power connection to TransGrid 330kV line 2 at Lobs Hole; and
3. Changes to project boundary for constructability and additional infrastructure

Current Status: Assessment

Interact with the stages for their names

  1. Prepare Mod Report
  2. Arrange Exhibition
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination