SSD Modifications
Determination
Mod 2 - Deferral of Salinity Reductions
Lithgow City
Current Status: Determination
Interact with the stages for their names
- SEARs
- Prepare Mod Report
- Exhibition
- Collate Submissions
- Assessment
- Recommendation
- Determination
Springvale Coal (Mod 2)
Attachments & Resources
Application (2)
EIS (5)
Response to Submissions (2)
Recommendation (7)
Determination (3)
Submissions
Showing 241 - 260 of 344 submissions
Zoe Colman
Object
Zoe Colman
Object
Blackheath
,
New South Wales
Message
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Amy Vos
Object
Amy Vos
Object
Austinmer
,
New South Wales
Message
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Claire Morrison
Object
Claire Morrison
Object
Mayfield
,
New South Wales
Message
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Zoe Butler
Object
Zoe Butler
Object
Clarence
,
New South Wales
Message
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Kathleen Abrahall
Object
Kathleen Abrahall
Object
SURREY HILLS
,
Victoria
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Tim Shakeshaft
Object
Tim Shakeshaft
Object
Newtown
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Ellen Ferrier
Object
Ellen Ferrier
Object
Wilsons Creek
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Greg Clarke
Object
Greg Clarke
Object
Middle Point
,
Northern Territory
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Alice Tims
Object
Alice Tims
Object
Newtown
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Dominic Sidoti
Object
Dominic Sidoti
Object
Sydney
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Sean Cranney
Object
Sean Cranney
Object
Matcham
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Hugh Fisher
Object
Hugh Fisher
Object
Enmore
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Malavika Singh
Object
Malavika Singh
Object
North Bondi
,
New South Wales
Message
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
James Kanagaratnam
Object
James Kanagaratnam
Object
Lithgow
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Steefan Contractor
Object
Steefan Contractor
Object
St Peters
,
New South Wales
Message
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Rachelle Reynolds
Object
Rachelle Reynolds
Object
Kingswood
,
New South Wales
Message
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Joshua Dabelstein
Object
Joshua Dabelstein
Object
Glebe
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Owen Vale
Object
Owen Vale
Object
Davidson
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Jana Michaels
Object
Jana Michaels
Object
Caulfield
,
Victoria
Message
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Jessica Wardhaugh
Object
Jessica Wardhaugh
Object
Katoomba
,
New South Wales
Message
Dear Sir/Madam,
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Objection to continued pollution of drinking water supplies by Springvale Mine Water (SSD 5594 - MOD 2)
I object to the proposed modification of the Springvale Mine consent that would allow mine water treatment to be deferred for two more years. This consent modification proposal would cause on-going pollution of the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources with toxic metal salts. Centennial Coal must not be granted legal relief arising from its foreshadowed default on the mine water discharge standards that it had previously agreed to with regulatory authorities.
Mine water discharges to Sawyers Swamp Creek that immediately flows into the Coxs River that is part of Sydney's drinking water catchment. Managing Director and CEO of Centennial Coal wrote to the Environment Protection Authority on May 29, 2015 to say that `Centennial acknowledges and agrees to the EPA's proposal for 700/900 EC limits as discussed in your letter'. The Planning Assessment Commission then placed these conditions in the September
2015 consent. I support the company's plans to remove mine water from Sydney's drinking water supplies by 30 June 2019 but Centennial Coal must be required to meet its consent obligations as agreed when the mine was approved.
Centennial Coal must install a temporary water treatment facility to meet the terms of its development consent so that mine water flowing into drinking water supplies receives at least a basic standard of treatment.
Further, this proposed consent modification is one of five modification proposals by Centennial Coal related to Springvale's mine water treatment.
The other proposals are: the mine water transfer, treatment and reuse at Mt Piper Power Plant; storage of treated mine water in Thompsons Creek Reservoir; the emplacement of waste from the water treatment plant; and effective treatment of highly polluting discharges from the emplacement area.
I request that these five proposals be considered together through the Department of Planning and Environment, and Planning Assessment processes.
Each proposal will not be properly understood unless these matters are assessed together.
Pagination
Project Details
Application Number
SSD-5594-MOD-2
Main Project
SSD-5594
Assessment Type
SSD Modifications
Development Type
Coal Mining
Local Government Areas
Lithgow City
Decision
Approved
Determination Date
Decider
IPC-N
Related Projects
SSD-5594-MOD-1
Determination
SSD Modifications
Mod 1 - Production Increase
Castlereagh Highway Blackmans Flat New South Wales Australia 2790
SSD-5594-MOD-2
Determination
SSD Modifications
Mod 2 - Deferral of Salinity Reductions
Castlereagh Highway Blackmans Flat New South Wales Australia 2790
SSD-5594-Mod-3
Determination
SSD Modifications
Springvale Coal MOD 3 - Aboriginal Heritage
Castlereagh Highway Blackmans Flat New South Wales Australia 2790
SSD-5594-Mod-4
Determination
SSD Modifications
MOD 4 - Rehabilitation Reforms
Castlereagh Highway Blackmans Flat New South Wales Australia 2790