Skip to main content

State Significant Development

Determination

Springvale Water Treatment Facility

Lithgow City

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Consolidated Consent

Consolidated Consent

Archive

Request for SEARs (1)

SEARS (1)

EIS (20)

Response to Submissions (2)

Amendments (2)

Recommendation (8)

Determination (3)

Approved Documents

Management Plans and Strategies (13)

Reports (4)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

There are no enforcements for this project.

Inspections

21/10/2020

10/05/2022

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 21 - 40 of 454 submissions
DEREK FINTER
Object
MUDGEE , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

I, my family, and I presume every member of your Department, drink water from the Sydney water supply. So take notice of the following.

Submission on the Springvale Water Treatment proposal (SSD 16_7592) The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

DEREK FINTER
Leeanne Frostick
Object
Neutral Bay , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

STOP THE CONTINUING EXPANSION OF COAL MINING AND START THINKING CREATIVELY OF ALTERNATIVE AND NON NATURE INVASIVE ENERGY SOURCES!

THE COAL INDUSTRY IS YESTERDAY'S INDUSTRY. THE FUTURE IS CLEAN GREEN AND ENVIRONMENTALLY SUSTAINABLE FOR EARTH'S SAKE!

Leeanne Frostick
jan westlake
Object
Ultimo , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

Mine water must not be simply treated to a minimum standard then released into the Cox's River catchment.
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment. This is totally unacceptable .

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

jan westlake
John Pettit
Object
Blackheath , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale mine must not be allowed to release up to 32 ML/day of treated mine water into the Coxs River which is part of Sydney's drinking water supply. The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.The Coxs River is not a drain for mine water.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

I have not made a reportable political donation and I agree that the Department may publish this submission. Thank you for the opportunity to make a submission on the Springvale Water Treatment proposal.

Yours sincerely,

John Pettit
Daniel Bolotin
Object
Thornbury , Victoria
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Daniel Bolotin
Karen Neubauer
Object
Bracken Ridge , Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Karen Neubauer
Alice Wood
Object
Bathurst , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Alice Wood
Geraldine Vaughan
Object
Neutral Bay , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

geraldine vaughan
Jenny Fox
Object
Blaxland , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Jenny Fox
Peter Green
Object
Faulconbridge , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Peter Green
Dorran & David Ackery
Object
Singleton , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Dorann & David Ackery
Sean Corrigan
Object
Trinity Beach , Queensland
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Sean Corrigan
Beverley Thompson
Object
wentworth falls , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Beverley Thompson
Tommy Wiedmann
Comment
Little Hartley , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

I'm a resident of Kanimbla Valley at the Coxs River, downstream from Lake Wallace. Currently platypus are living in the river.

I welcome the proposal to treat mine water before being released into the environment. However, the Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources.
Mine water must not be simply treated to a minimum standard then released into the catchment.

The Springvale mine must not be allowed to release up to 32 ML/day of treated mine water into the Coxs River which is part of Sydney's drinking water supply. The Coxs River is not a drain for mine water. The river must be restored to health, because it flows through our Blue Mountains World Heritage Area. The release of treated mine water will increase the nutrient status of the Coxs River and possibly lead to massive outbreaks in aquatic weeds or algal blooms downstream.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Tommy Wiedmann
Bruce Cameron
Object
Sun Valley , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

I am writing to you to express my very real and scientifically backed concerns over the Springvale operations and associated treatment works. The time has come locally and worldwide to realise what you and I are doing to the environment is in essence the start of the end. Climate is the key and coal burning is only adding to the horrible predicament we are in.

I urge you to cease polluting our rivers and creeks.

You cannot rip up the floorboards and burn them for fuel tonight and walk on the bearers and joists for evermore...as a government you have a duty to protect the community.

Regards
Bruce Cameron
Peter Drinkall
Object
Wallerawang , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Peter Drinkall
Andrew Valja
Object
Dargan , New South Wales
Message
These coal mining companies have been getting away with dumping polluted mine water for decades into our waterways, some of which flow into water supply dams. They have not voluntarily done the right thing, which would be to treat the water to a standard that will have a neutral or beneficial affect on the waterways. It is time for these companies to be forced by regulation to do what is best for the environment, not just what is best for their company profits.
Springvale should treat the water to a much higher level of purity without the usual metals and salts (including exceedances in arsenic in the past year) that they have until now been disposing of in our rivers. Water temperature and PH are also an issue.
Springvale is not the only mine doing this in that area, as Angus Place Colliery, Clarence Colliery, Baal Bone Colliery, (and probably others) are disposing of mine discharge water into waterways, with similarly poor standards of water quality.
The current Springvale proposal is the time to finally raise the standards for discharged coal mine water, for now and the future.
This is even more important now as there are proposals by Springvale and Angus Place to extend the mining areas and to increase the annual production, which will lead to an increase in the combined amount of water discharged.
Ellie Hinder
Object
Princes Hill Victoria , Victoria
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Ellie Hinder
Elizabeth Vesely
Object
Riverwood , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. Mine water must not be simply treated to a minimum standard then released into the catchment.

Wangcol Creek is already contaminated. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

The water treatment plant must not be built for discharge into the environment. It can be designed as a closed system with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

Elizabeth Vesely
Kay Bushnell
Object
Mudgee , New South Wales
Message
Mining and Industry Projects
NSW Department of Planning and Environment GPO Box 39 Sydney NSW 2001

Dear Sir/Madam,

Submission on the Springvale Water Treatment proposal (SSD 16_7592)

HOW DARE MINING WATER RESIDUE THREATEN THE COXS RIVER CATCHMENT.
The Springvale water treatment proposal must be greatly improved if it is to adequately protect the Coxs River catchment, the Greater Blue Mountains World Heritage Area and Sydney's drinking water resources. MINE WATER MUST NOT BE SIMPLY TREATED TO A MINIMUM STANDARD THEN RELEASED INTO THE CATCHMENT.

WANGOOL CREEK IS ALREADY CONTAMINATED. Discharges from the proposed treatment plant would worsen this situation and send a plume of salt down the Coxs River that is part of Sydney's drinking water catchment.

The treatment proposal must maximise mine water use by storing it for future periods of high demand by the Mt Piper Power Plant. Water treatment must be decoupled from the power plant's coal consumption to prevent an outcome where a reduction in coal-fired electricity generation would cause an increase in mine water pollution.

THE WATER TREATMENT CAN BE DESIGNED AS A CLOSED SYSTEM WITH with treated mine water stored in Thompsons Creek Reservoir which has sufficient capacity to accommodate mine water from both Springvale and Clarence mines for future power plant use.

To take advantage of future mine water transfer upgrades, the proposed pipeline from Springvale to Mt Piper power plant should have sufficient capacity to accommodate mine water from Clarence Colliery.

Runoff from the Springvale Coal Services and fly ash emplacement areas also must be collected and treated for use in the power plant.

Any additional pipeline construction on Newnes Plateau for the mine water transfers must follow the existing pipeline alignment to minimise further damage to endangered ecological communities and pagoda landscapes.

I URGE YOU TO PROTECT THE BLUE MOUNTAINS WORLD HERITAGE AREA AND SYDNEY'S DRINKING WATER AGAINST THIS POSSIBLE CONTAMINATION.

Kay Bushnell

Pagination

Project Details

Application Number
SSD-7592
Assessment Type
State Significant Development
Development Type
Water supply & management
Local Government Areas
Lithgow City
Decision
Approved
Determination Date
Decider
IPC-N
Last Modified By
SSD-7592-Mod-11
Last Modified On
28/03/2025

Contact Planner

Name
Anthony Ko