Skip to main content

State Significant Infrastructure

Response to Submissions

Victoria to NSW Interconnector West

Edward River

Current Status: Response to Submissions

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Development of a new 500kV double circuit transmission lines between the NSW and Victoria border near Murrabit and the new Dinawan substation; and replacement of the existing 330kV transmission line between Wagga substation and new Gugaa substation.

EPBC

This project is a controlled action under the Environment Protection and Biodiversity Conservation Act 1999 and will be assessed under the bilateral agreement between the NSW and Commonwealth Governments, or an accredited assessment process. For more information, refer to the Australian Government's website.

Attachments & Resources

Notice of Exhibition (1)

Application (7)

SEARs (20)

EIS (33)

Response to Submissions (1)

Agency Advice (26)

Submissions

Filters
Showing 21 - 40 of 123 submissions
Name Withheld
Object
swan Hill , Victoria
Message
Landowners remain concerned about public liability insurance adequacy near renewable infrastructure. Coverage may fall short of asset values, exposing farmers to risk . This critical issue is unresolved and financially dangerous.
Name Withheld
Object
Swan Hill , Victoria
Message
Construction and maintenance may spread PFAS (per- and polyfluoroalkyl substances) from fire-fighting foams or materials. Such contamination is persistent, toxic, and harmful to soil, water, livestock, and human health. No sufficient PFAS prevention or monitoring strategies are present.
Colin McCrabb
Object
Wanganella , New South Wales
Message
Word document attached
Attachments
Name Withheld
Object
Gannawarra , Victoria
Message
The EIS fails to meaningfully address decommissioning. Who will bear the cost decades from now when towers and cables need removal? Without clear plans or obligations, local communities could be left facing environmental blight or liability.
Name Withheld
Object
Moulamein , New South Wales
Message
Transmission developers repeatedly claimed the route couldn’t change, yet it has been altered at least five times. This inconsistency erodes trust and suggests flexibility in planning for political convenience rather than community input. Such shifting claims are deceptive and unacceptable.
Name Withheld
Object
Barham , New South Wales
Message
I object over the minimal and cursory community consultation. As noted in the NSW REZ inquiry, there has been “inadequate consultation” resulting in mental health strains and social fragmentation .
Locals were not properly engaged or consulted about route alternatives or the scale of impact, undermining social licence and democratic trust.
jim gleeson
Object
swan hill , Victoria
Message
see attachment
Attachments
Name Withheld
Object
Moulamein , New South Wales
Message
The required substations, including Dinawan and Gugaa, will consume and industrialise large areas. Agricultural land will be lost, fragmenting farm operations. The impact on pasture, cropping, and animal movement is significant and under-assessed.
Name Withheld
Object
BARHAM , New South Wales
Message
The proposed 500 kV lines and substations will severely degrade scenic rural landscapes. Farmland views will be dominated by huge towers and industrial structures, affecting property values, tourism, and community character. The Environmental Impact Statement insufficiently addresses visual harm.
Name Withheld
Object
Moulamein , New South Wales
Message
I raise serious concern about infrasound from high-voltage lines. Though often dismissed, long-term exposure to low-frequency noise may cause sleep disturbance, headaches, and stress, particularly for nearby residents. The environmental impact statement appears to neglect health assessments for infrasound.
Name Withheld
Object
Moulamein , New South Wales
Message
This project claims to improve energy reliability, yet it chiefly connects intermittent solar and wind sources, which depend on weather conditions. On cloudy or windless days or during “wind droughts”, these sources can’t supply sufficient power.
Spending billions on infrastructure that doesn’t guarantee reliability during peak demand is misguided and fiscally irresponsible.
Name Withheld
Object
Moulamein , New South Wales
Message
I object due to the immense cost blowouts associated with VNI West. Originally estimated at ~$3.9 billion, costs are now projected between $7.6 billion and potentially $11.4 billion . Such ballooning costs suggest an unreliable economic foundation and risk passing future burdens onto electricity consumers. The project’s scale and escalating price tag threaten its financial feasibility and undermine public trust in the transition.
HumeLink Alliance Incorporated
Object
MERRILL , New South Wales
Message
Please see submission attached
Attachments
Name Withheld
Object
Moulamein , New South Wales
Message
I strongly object to the VNI West development on the grounds of elevated fire risk. As highlighted in the NSW Legislative Council report, communities within Renewable Energy Zones (REZs) face “devastating” bushfires, with land cleared for infrastructure likely increasing ignition points and hampering firefighting access and effectiveness . Transmission lines, substations, and maintenance tracks will introduce additional hazards. The fire-prone nature of the region, combined with climate-change-driven extremes, makes this a serious public safety concern. Ignoring such risks is irresponsible and potentially catastrophic.
Name Withheld
Object
GUYRA , New South Wales
Message
To the Proponent, NSW Electricity Networks Operations Pty Ltd (TransGrid) and Council Areas: Murrumbidgee, Murray River, Edward River, Wagga Wagga
The experiment is over re 500kv Overhead Transmission Lines.
Research says so.
Where is yours, nsw.gov.au, gov.au, vic.gov.au ? Where is it ?
You don't have it do you.
Who are you people ?
I Demand a Full Investigation of 500kv Overhead Transmission Lines. Who is planning a new 500kV double circuit Interconnector Transmission Lines from the Victorian border at Murrabit to the new Dinawan Substation in NSW near Jerilderie ?
Who ? Who ? Planner is it ? Where is his research, research on 500kv Overhead Transmission Lines please.
I Demand a Full Investigation of Effects of 500 kv Overhead Transmission Lines on Australians exposed to 500kv Overhead Transmission Lines.
Research says cease and Desist 500kv Overhead Transmission Lines.
Yet someone's are to be irresponsible aren't they.
Who are these people being irresponsible toward their Fellow Australians that do Include children yes.
Is it the planner ? Is it ? Absolutely.
Are the councils Complicit ? Yes.
Councillors also ? Yes. Of course.
Ministers too ? Absolutely.
OK. Where is the research on 500kv Overhead Transmission Lines effects on the Health and Well-being of Australians ? Show it to the People living near 500kv Overhead Transmission Lines.
Halt All Further development of VNI West.
I Demand an Immediate Moratorium on 500kv Overhead Transmission Lines in Australia, yes, Australia.
I also I Demand the Resignation of Minister Allan and Minister D'Ambrosio for breach of human rights.
Yes.
Today I was SHOCKED to feel the anger expressed by our Rural Communities Victorian toward both Prime Minister and Minister Allan.
How Dare politicians rule over their Fellow Australians.
Minister Allan and vic.gov.au all are breaching human rights, yes.
To force EMR infrastructure into homes and workplaces of Fellow Australians who grow Food for the Nation every day every day every day on their properties is a Crime Against Humanity. Is.
I Demand an Immediate Moratorium on 500kv Overhead Transmission Lines in Australia Immediately. Research says so.
I Demand a Full investigation of the effects of 500kv Overhead Transmission Lines on Australians living within 80 metres of any 500kv Overhead Transmission Lines.
Council Areas Murrumbidgee, Murray River, Edward River, Wagga Wagga be warned.
EMR issues include the now upgraded 500kv Overhead Transmission Lines as potential risks to human health and well-being.
Research is ?? Where is it ??
Where ?? Where ?? On Duck Duck Go etc.
Watch out councils. You are fully accountable and need to be held accountable if if if any 500 kV Overhead Transmission Lines come within 40 metres of a biological human, existing as a Form Field Phenomena upon Earth, once natural, not now.
500 kV Transmission Lines Exposure time can be under 3 hours to over 8 hours, dependant on the individual.
Show me your research you have collected on 500kv Overhead Transmission Lines effects on humans living or working within 80 metres.
Some humans are more sensitive than that. Some are. Some are.
Children.
Children.
Children.
In case you didn't know, farmers live and work at home you see.
Some live and work there 24/7 day after day year after year.
Show me your research on EMR Effects on Animals With Nervous Systems please in connection to 500kv Overhead Transmission Lines.
Risks are too high you see.
Risks.
Risks. I say Risks are too high re 500 kV Overhead Transmission Lines I Demand be Banned in Australia Immediately.
Who will help ? Who ?
Politicians will be held accountable of course.
As will mayors , councils , Councillors, yes.
Time they were isn't it.
These days there is No excuse to be ignorant about EMR Effects on Animals With Nervous Systems.
240kv Transmission Lines are about the Limit of Safety you see.
I Demand a Full Investigation of the public exposed to any 500 kV Overhead Transmission Line who live or work within 40 metres of, and out to 80 metres for the sensitive community being the Children now living in a quite Unreal World to those children who have lived a Wireless Life over their entire life, no, but over half their life or so.
A World we live in changes due to gov.au.
Who ever asked us, the Australian People, did we need 500 kV Overhead Transmission Lines or even 320kv.
Who makes these decisions is a Question.
I Demand a Full investigation into the few humans deciding the Futures of their Fellow human beings and Fellow Australians that Include children yes.
I say Cease and Desist 500 kV Overhead Transmission Lines Immediately Immediately Immediately in Australia.
That does include Victoria.
The Victorian Government breaches human rights. Oh Yes they do. Have. Still do. Include NSW Government.
It is about time politicians were held fully accountable for all the decisions made affecting their Fellow Australians, which includes children.
When will it be time ?
Who will be Held Accountable ?
Minister Bowen of course.
Minister Watt plus Minister Plibersek of course.
Minister Allan, the female Hitler in a team experimenting on their Fellow Australians. Yes. Experimenting.
Who else ? All councils, yes, yes, All councils , yes.
We cannot get a Say. Do you understand ? There is No excuse for being ignorant about EMR Effects on Animals With Nervous Systems.
I do not know how you get away with it.
I want to know how you get away with it.
There is No excuse for being ignorant when it comes to the Health and Well-being of your Fellow Australians that do Include Children yes Children, children, being experimented on worse than Ever before.
How Dare You All.
Planners in gov.au are to be Held Fully Accountable for Harm and Loss to their Fellow Australians including children.
I understand Fields of Harm you see.
That is my research you see. 15 years researching EMR Effects on Animals With Nervous Systems says Ban Outright 500 kV Overhead Transmission Lines Immediately in Australia. The experiment is Finished. I await the results gov.au must offer me.
That includes from councils Enabling any 500kv Overhead Transmission Lines anywhere near children, children, children.
I live in Grief at How this World changes.
Children must be Cared for.
Where is the Risk Assessment research re 500kv Overhead Transmission Lines please? Where is it ? Where is it ?
We really have No rights. That is Wrong.
To have No rights is wrong. I do Demand those responsible be Held Fully Accountable.
EMR issues are Real. Yes, Real.
Ban AI Today.
Cease and Desist any need for 500 kV Overhead Transmission Lines in Australia Immediately. Ban AI Immediately. Surely you know why.
Surely you know why.
Surely.
Net Zero I Demand be Under Investigation Immediately. Unnecessary excess Infrastructures reasons.
If you understand EMR Effects on Animals With Nervous Systems then it will be an Immediate Moratorium on 500kv Overhead Transmission Lines in Australia.
I Demand those responsible for Enabling 500kv Overhead Transmission Lines be Held Fully Accountable and be under investigation.
Children are in View.
Children, born into an Unnatural world. Unnatural. A completely EMR World children live in now. Slow down, gov.au, nsw.gov.au, vic.gov.au. You have No idea what you are doing to your Fellow Australians living and working environments and must be held fully accountable. Yes.
Mental anxiety can be an EMR Syndrome issue. Mental anxiety. Cancers too. Nervous Systems are in View that are interconnected all parts of the body mind and spirit of a being, animal, living on Earth, exposed to Hideous Harming EMR Fields of Harm worsening why ? Why ? Why ? Why ?
I need a Full investigation into 500 kV Overhead Transmission Lines in Australia and an Immediate Moratorium on All planned 500kv Overhead Transmission Lines in Australia until this Full investigation has been completed.
Greg Mildren
Object
Tungkillo , South Australia
Message
Given cost misrepresentation, missing EDC report, substantial clearing, major agricultural/aviation constraints, material visual intrusion and cumulative impacts, the application should be refused, or at minimum re-exhibited with corrected information and a SEARs-compliant alternatives assessment including route-specific and partial-underground options.
Attachments
Greg Mildren
Object
Tungkillo , South Australia
Message
Given cost misrepresentation, missing EDC report, substantial clearing, major agricultural/aviation constraints, material visual intrusion and cumulative impacts, the application should be refused, or at minimum re-exhibited with corrected information and a SEARs-compliant alternatives assessment including route-specific and partial-underground options.
Attachments
Emma Burke
Object
UPPER LANSDOWNE , New South Wales
Message
Strongly object as VNI West is not required, will not happen! I object to the health, environmental, fiscal and mental health impact of this project.
Name Withheld
Object
Còolah , New South Wales
Message
Stop destroying rural regions for the benefit of foreign companies and rent seeking Australians.
This transmission project will enable RE developers to spread like a cancer across our rural regions. The environmental damage being sanctioned by State and Federal Government under the so called energy transition is horrific. We want a corruption inquiry into the individuals profiting from this project.
Emma Bowman
Object
DUNEDOO , New South Wales
Message
Please find attached objection.
Attachments

Pagination

Project Details

Application Number
SSI-72887208
EPBC ID Number
2024/09871
Assessment Type
State Significant Infrastructure
Development Type
Electricity supply
Local Government Areas
Edward River

Contact Planner

Name
Anthony Ko