Westlink Industrial Estate - Stage 1

Penrith

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Construction of 2 warehouse buildings and ancillary office space, bulk earthworks and vegetation clearing, construction of roads and external road upgrades, site servicing and stormwater infrastructure, landscaping and subdivision.

Consolidated Consent

SSD-9138102-Mod-4 Consolidated Consent

Archive

Notice of Exhibition (1)

SEARs (3)

EIS (34)

Response to Submissions (70)

Agency Advice (22)

Amendments (31)

Additional Information (42)

Recommendation (2)

Determination (3)

Approved Documents

Management Plans and Strategies (78)

Notifications (13)

Other Documents (7)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

Development Control Order issued to ESR Developments (Australia) Pty Ltd (SSD-9138102) Penrith LGA

On 18 June 2024, a delegate for the Minister for Planning issued a Development Control Order to ESR Developments (Australia) Pty Ltd (ESR) in relation to development at 200 Aldington Road, Kemps Creek. Under the Order, ESR is refrained from carrying out work in the area identified as ‘undeveloped land’ in the consent.

Penalty Notice issued to Richard Crookes Constructions Pty Ltd (SSD-9138102) Penrith LGA

On 19 November 2024, NSW Planning issued a $15,000 Penalty Notice to Richard Crookes Constructions Pty Limited (RCC) for failing to implement the approved Construction Traffic Management Plan (CTMP) at the Westlink Industrial Estate – Stage 1 development. On 4 June 2024, RCC failed to distribute the approved traffic routes to drivers prior to their arrival at the site in contravention of the CTMP. The approved traffic routes were put in place to improve road safety and amenity by avoiding a local school and other sensitive land uses, providing a safer option for vehicles leaving and entering Mamre Road. NSW Planning will continue to monitor compliance with the approved traffic routes at the development.

Inspections

30/05/2023

27/06/2023

25/07/2023

31/10/2023

15/11/2023

20/02/2024

5/03/2024

14/03/2024

26/03/2024

8/05/2024

16/05/2024

28/05/2024

12/06/2024

13/06/2024

10/07/2024

1/08/2024

24/09/2024

31/10/2024

12/11/2024

14/11/2024

12/12/2024

27/02/2025

27/02/2025

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 1 - 15 of 15 submissions
Steven Broussos
Support
GREENACRE , New South Wales
Message
This will be good for the economy
ENVIRONMENT PROTECTION AUTHORITY
Comment
,
Message
No Comment Letter attached
Attachments
Tony Oliva
Comment
Kemps Creek , New South Wales
Message
Hi ,as a neighbouring property to the development Ihave a few concerns about the impact this site will have on my property and our quality of living once constuction begins .
will there be any upgrades to our road , will we have any privacy from the constuction work , will it be very noisy and will it potentially block my f
property off any future development . I am not objecting at this point I would just like some more information on how things are going to be done as my property is directly next to this site , thank you
NSW Rural Fire Service
Comment
SYDNEY OLYMPIC PARK , New South Wales
Message
See attached
Attachments
Name Withheld
Comment
MOUNT VERNON , New South Wales
Message
On viewing the plan on the Planning Portal it appears the buildings called warehouse 4a and 4b encroach on the 30 meter building setback line on the south eastern boundary.
Could you please ensure this is not the case?
Endeavour Energy
Comment
ROADS AND MARITIME SERVICES DIVISION
Comment
PARRAMATTA , New South Wales
Message
Please see the attached response
Attachments
TRANSPORT FOR NSW
Comment
Haymarket , New South Wales
Message
See attached.
Attachments
Biodiversity and Conservation Division
Comment
PARRAMATTA , New South Wales
Message
Please find attached EES comments
Attachments
Western Sydney Airport
Comment
,
Message
Detailed comments are provided in the attached letter, dated 19 July 2021. WSA's position is that:
- Conditions should be imposed on any consent in respect to airspace operations, noise, wildlife management and monitoring.
- The mitigation measures should be updated to include wildlife management.
- The size of the onsite detention pond should be clarified and consistently applied throughout the EIS documentation.
- A condition should be imposed limiting the size of the initial development, consistent with the advice within the Construction Traffic Management Plan.
Attachments
Western Sydney Planning Partnership
Comment
PARRAMATTA , New South Wales
Message
Attached
Attachments
Heritage NSW – Aboriginal cultural heritage (ACH)
Comment
Sydney , New South Wales
Message
See Heritage NSW Aboriginal Cultural Heritage Regulation Advice attached.
Attachments
Penrith City Council
Comment
,
Message
Good Morning,

Please find attached correspondence from Penrith City Council.

Kind regards
Simone Muscat
Secretary - Management Team
Attachments
Water Group
Comment
,
Message
Please see letter attached.
Attachments
Sydney Water
Comment
PARRAMATTA , New South Wales
Message
See attachment
Attachments

Pagination

Project Details

Application Number
SSD-9138102
Assessment Type
State Significant Development
Development Type
Warehouse or distribution centres
Local Government Areas
Penrith
Decision
Approved
Determination Date
Decider
Director
Last Modified By
SSD-9138102-Mod-4
Last Modified On
11/03/2025

Contact Planner

Name
David Schwebel