Alteration of Stormwater Drainage System 2B Parson Street, Ulladulla

Shoalhaven

The proposed activity is the diversion of the stormwater management system within Lot 7 SP 75314, 2B Parson Street, Ulladulla. Physical works would involve:
• the demolition of the existing 900 mm reinforced concrete pipe (RCP) – approximately 25 metres in length
• installation of new 1050 mm RCP within a new drainage easement within Lot CP (7) – approximately 25 metres in length
• replacement of RCP with 600 mm RCP – approximately 20 metres in length
• installation and/or reconstruction of stormwater pits to facilitate the proposed diversions
• associated earthworks
• change in use from parking area to parking area and stormwater management
• removal of five trees from the adjacent Shoalhaven City Council managed Crown Land reserve (Lot 7012 DP 1031353).

Review of Environmental Factors (REF) (1)

The approved project is described in the REF, as modified by any associated decision statement (see supporting documents).
Review of Environmental Factors
Review of Environmental Factors REF - alterations to stormwater system - Lot 7 SP 25314 - 2B Parson Street Ulladulla
Date : Mon, 13/03/2023 - 10:51

Activity Details

Reference number
P5-2023-23
Proponent(s)
Shoalhaven City Council
Address
2B Parson Street Ulladulla 2539
Legislation
TISEPP (State Environmental Planning Policy (Transport & Infrastructure) 2021)
Activity Type
Stormwater management systems
Decision
Approved
Determination date