S4.55(2) Modification Application
Determined
55 Grafton Street BONDI JUNCTION
Sydney Eastern City Planning Panel
Modification to the approved development including a reduction in the number of apartments from 106 to 95, internal reconfiguration of units and increase in floor space
Determination and Statement of Reasons (1)
Determination and Statement of Reasons
PPSSEC175 - Determination & SOR
Council Assessment Report (1)
Council Assessment Report
(corrected 29082022) SECPP Assessment Report - DA-155-2018-A - 55 Grafton Street BONDI JUNCTION
Record of Briefing (1)
Record of Briefing
PPSSEC-175 - Record of Briefing
Other (7)
BASIX certificate
BASIX Certificate - 55 Grafton Street Bondi Junction
Conflict of interest declaration
PPSSEC-175 Gabrielle Morrish
Conflict of interest declaration
PPSSEC-175 Jan Murrell
Conflict of interest declaration
PPSSEC-175 - Carl Scully
Conflict of interest declaration
PPSSEC-175 Jeremy Swan
Other
NatHERS ReStamped Drawings - 55 Grafton St Bondi Junction
Other
NatHERS Individual Certificates - 55 Grafton Street Bondi Junction
Project Details
DA
number
DA-155/2018/A
Planning panel reference number
PPSSEC-175
Capital investment value
$69,663,756
Project Address
55 Grafton Street Bondi Junction 2022
Lodgement date
Referral date
Local government
Waverley Council
Type of matter
DA
Determination outcome
Approved
Determination Date