CIV > $5M - Private infrastructure and community facilities
Under assessment
Electricity Generating Works (solar farm) and Battery Energy Storage System (BESS)
Western Regional Planning Panel
Development of a 5MW solar farm comprising 15,600 solar modules supported by an inverter station and battery energy storage system enclosed within security fencing and landscape screening
Record of Briefing (1)
Record of Briefing
PPSWES-274 Record of Preliminary Briefing
Record of Site Visit (1)
Record of Site Visit
PPSWES-274 - Record of Site Inspection
Project Details
DA
number
DA 761/2024(1)
Planning panel reference number
PPSWES-274
Capital investment value
$7,677,088
Project Address
25 Lone Pine Avenue Orange 2800
Lodgement date
Referral date
Local government
Orange City Council
Type of matter
DA