Designated Development - Waste Facility

Determined

RPP - DESIGNATED & NOMINATED INTEGRATED Change of Use to Resource Recovery Facility

Hunter & Central Coast Regional Planning Panel

ReDirect propose to operate a best practice Resource Recovery Facility at 33 Pile Road, Somersby. The facility will have a maximum processing capacity of 99,000 tonnes per annum for processing principally non-putrescible materials. ReDirect Recycling Pty Ltd propose to operate the facility 24 hours, 7 days per week, in line with previous approvals for the site.
The proposed development will utilise the approved warehouse facility, with minor modifications and change of use into a fully integrated resource recovery facility. The development of the new warehouse was approved on 16th December 2019 under DA56372/2019.

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
Completed declaration forms PPSHCC-97

Council Assessment Report (1)

Council Assessment Report
221006 KEYLAN DA_63453_2021 Assessment Report

Attachments to Council Assessment Report (2)

Attachment – amended plans
Attachment 3 - Civil Plans
Attachment – amended plans
Attachment 2 - Architectural Plans

Record of Briefing (2)

Record of Briefing
PPSHCC-97 - Kick off Record of Briefing
Record of Briefing
PPSHCC-97 - 33 Pile Road- Panel Presentation

Other (4)

Other
221014 KEYLAN DA_63453_2021 Memo
Other
Attachment 4 - EIS Report
Other
221006 KEYLAN DA_63453_2021 Conditions
Other
EPA General Terms of Approval _ - Notice 1618857 - 18.05.2022

Project Details

DA number
63453/2021
Planning panel reference number
PPSHCC-97
Capital investment value
$2,878,000
Project Address
33 Pile Road Somersby 2250,3-5 Pinnacle Place Somersby 2250
Lodgement date
Referral date
Local government
Central Coast Council
Type of matter
DA
Determination outcome
Approved
Determination Date