CIV > $5M - Council interest

Determined

Torrens Title Subdivision into 40 Industrial Lots

Sydney Western City Planning Panel

Torrens Title Subdivision into 40 Industrial Lots, 1 Stormwater Management Infrastructure Lot & Public Roads including Land Remediation, Earthworks, Civil Engineering Works & Public Domain Landscaping

Determination and Statement of Reasons (2)

Determination and Statement of Reasons
DSoR PPSSWC-243 Penrith DA22-0318 - 158-164 Old Bathurst Road Emu Plains 17.4.24
Determination and Statement of Reasons
Determination and Statement of Reasons - PPSSWC-243 Penrith DA22-0318 - 158-164 Old Bathurst Road Emu Plains - Torrens Title S

Completed Panel Declaration forms (1)

Completed Panel Declaration forms
Panel Declarations PPSSWC-243

Council Assessment Memorandum (2)

Council Assessment Memorandum
PPSSWC-243 - Further Memorandum to SWCPP from Landmark Planning - DA22_0318
Council Assessment Memorandum
PPSSWC-243 - Memorandum to SWCPP from Landmark Planning - DA22_0318 at 158-164 Old Bathurst Road Emu Plains - 26.02.2024

Council Assessment Report (2)

Council Assessment Report
Council Assessment Report - PPSSWC-243 - DA22_0318 - ROCLA
Council Assessment Report
Council Assessment Report Cover Sheet - PPSSWC-243 - DA22_0318

Attachments to Council Assessment Report (33)

Attachment to assessment report
Attachment 10 - Flood Impact Assesseement 11 October 2022 - DA22 0318
Attachment to assessment report
Attachment 17.1 - BDAR Figures 10 October 2022 - DA22 0318
Attachment to assessment report
Attachment 4 - Landscape Plans 7 October 2022 - DA22 0318
Attachment to assessment report
Attachment 12 - Geotechnical Report 10 January 2024 - DA22 0318
Attachment to assessment report
Attachment 3 - Civil Drawings Issue D 17 October 2022 - DA22 0318
Attachment to assessment report
Attachment 11 - Flood Emergency Response Stratgey 7 October 2022 - DA22 0318
Attachment to assessment report
Attachment 13 - Arboriculture Impact Assessment 1 September 2022 - DA22 0318
Attachment to assessment report
Attachment 6 - Stormwater Management Plan 27 September 2022 - DA22 0318
Attachment to assessment report
Attachment 8 - Transport Impact Assessment 12 April 2023 - DA22 0318
Attachment to assessment report
Attachment 9 - Visual Impact Assessment 7 October 2022 - DA22 0318
Attachment to assessment report
Attachment 1 - Statement of Environmental Effects 8 April 2022 - DA22 0318
Attachment to assessment report
Attachment 14 - Arboriculture Impact Assessment Appendix 1 September 2022 - DA22 0318
Attachment to assessment report
Attachment 7 - Waste Management Plan 4 April 2022 - DA22 0318
Attachment to assessment report
Attachment 2 - Subdivision Concept Plan 14 February 2024 - DA22 0318
Attachment to assessment report
Attachment 23.3 - Applicants RFI Response Letter 17 October 2022 - DA22 0318
Attachment to assessment report
Attachment 16 - Signals Advisory Note SCT Consulting 19 December 2023 - DA22 0318
Attachment to assessment report
Attachment 18 - Response DPE-Water GTAs Response Letter 29 March 2023 - DA22 0318
Attachment to assessment report
Attachment 23.4 - Applicants RFI Response Letter 14 July 2023 - DA22 0318
Attachment to assessment report
Attachment 17 - BDAR 10 October 2022 - DA22 0318
Attachment to assessment report
Attachment 23.2 - Applicants RFI Response Letter 5 October 2022 - DA22 0318
Attachment to assessment report
Attachment 25 - Applicants Letter Removal of Driveway 2 February 2024 - DA22 0318
Attachment to assessment report
Attachment 23.1 - Applicants RFI Response Letter 20 September 2022 - DA22 0318
Attachment to assessment report
Attachment 21 - Response Sydney Trains Letter 15 June 2022 - DA22 0318
Attachment to assessment report
Attachment 20 - Response Sydney Water Letter 3 June 2022 - DA22 0318
Attachment to assessment report
Attachment 23.5 - Applicants RFI Response Letter 14 February 2024 - DA22 0318
Attachment to assessment report
Attachment 26 - Applicants Letter Removal of Driveway Landowners 2 February 2024 - DA22 0318
Attachment to assessment report
Attachment 22 - Response TfNSW Letter 30 January 2024 - DA22 0318
Attachment to assessment report
Attachment 24 - Applicants Email Acceptance of Maintenance Lot 32 11 October 2022 -DA22 0318
Attachment to assessment report
Attachment 17.2 - BDAR Tables 10 October 2022 - DA22 0318
Attachment to assessment report
Attachment 15 - Traffic Signals 11 October 2022 - DA22 0318
Attachment to assessment report
Attachment 5 - Retaining Wall Longitudinal Section 3 February 2023 - DA22 0318
Attachment – recommended conditions of consent
PPSSWC-243 - Fast Track Conditions Summary DA22_0318 - 2 April 2024
Attachment – recommended conditions of consent
PPSSWC-243 - Commentary for Conditions DA22_0318- 2 April 2024

Record of Briefing (3)

Record of Briefing
Record of Deferral - PPSSWC-243 - 58-164 Old Bathurst Road Emu Plains
Record of Briefing
PPSSWC-243 ROB
Record of Briefing
Record of Briefing - PPSSWC-243 - 27 June 2022

Other (3)

Other
Conditions Table Report for SWCPP DA22 0318
Other
Mound Retention Plan
Other
11584_WSPPMeeting_Mound

Project Details

DA number
DA22/0318
Planning panel reference number
PPSSWC-243
Capital investment value
$9,095,541
Project Address
158-164 Old Bathurst Road Emu Plains 2750
Lodgement date
Referral date
Local government
Penrith City Council
Type of matter
DA
Determination outcome
Approved
Determination Date