State Significant Development
Flyers Creek Wind Farm
Blayney Shire
Current Status: Determination
Interact with the stages for their names
- SEARs
- Prepare EIS
- Exhibition
- Collate Submissions
- Assessment
- Recommendation
- Determination
Construction and operation of a 88-132MW wind farm, with up to 44 turbines and associated infrastructure at Flyers Creek, approximately 20 kilometres south of Orange.
Consolidated Consent
Modifications
Archive
Application (8)
DGRs (3)
EA (40)
Response to Submissions (6)
Recommendation (5)
Determination (2)
Approved Documents
Management Plans and Strategies (26)
Reports (1)
Independent Reviews and Audits (3)
Other Documents (5)
Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.
Complaints
Want to lodge a compliance complaint about this project?
Make a ComplaintEnforcements
Penalty Notice issued to Green Light Contractors Pty Ltd (MP08_0252) Blayney Shire LGA
On 27 September 2022, the department issued a $15000 Penalty Notice to Green Light Contractors Pty Ltd, the construction contractor for the Flyers Creek Wind Farm, for the clearing of an individual mature Eucalyptus Canobolensis tree, required to be retained, whilst undertaking clearing for the power line easement corridor. The department will continue to monitor the development for compliance with conditions of consent.
Inspections
15/07/2022
9/02/2023
1/03/2023
4/05/2023