Skip to main content

State Significant Infrastructure

Determination

Sydney Metro West - Concept and Stage 1 (major civil construction between Westmead and The Bays)

Burwood

Current Status: Determination

Interact with the stages for their names

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Sydney Metro West will service Westmead, Greater Parramatta, Sydney Olympic Park, The Bays Precinct and the Sydney CBD linking new communities to rail services with intermediate stations.

Consolidated Approval

SSI 10038 MOD 6 - Consolidated Approval

Archive

Application (1)

SEARs (1)

EIS (52)

Response to Submissions (6)

Amendments (1)

Determination (3)

Approved Documents

Management Plans and Strategies (161)

Agreements (1)

Community Consultative Committees and Panels (3)

Reports (12)

Independent Reviews and Audits (7)

Other Documents (26)

Note: Only documents approved by the Department after November 2019 will be published above. Any documents approved before this time can be viewed on the Applicant's website.

Complaints

Want to lodge a compliance complaint about this project?

Make a Complaint

Enforcements

Penalty Notices (3) and Official Cautions (2) issued to Acciona Ferrovial joint venture (SSI-10038) Canada Bay LGA

On 11 December 2023, NSW Planning issued three $15,000 Penalty Notices and two Official Cautions to Acciona Ferrovial joint venture (AFJV) for failing to comply with conditions of the Sydney Metro West approval. AFJV was issued one Penalty Notice for not having the required noise mitigation measures in place before commencing out of hours cavern excavation at the Burwood North station construction site. AFJV was issued a further two Penalty Notices and one Official Caution for not having the noise and traffic mitigation measures described in their management plans in place during bulk excavation at the Five Dock West station construction site. AFJV was issued a further Official Caution for not publishing the required traffic management plan on their website. AFJV has revised its construction program to minimise further construction activities at the Five Dock West site.

Penalty Notice issued to Gamuda Berhad (SSI-10038) City of Parramatta LGA

On 23 July 2024, NSW Planning issued a $15,000 Penalty Notice to Gamuda Berhad (Gamuda) for failing to ensure effective noise mitigation was in place at the Westmead station construction site for out of hours compressor noise. Gamuda commissioned a pair of compressors in June 2023 and identified compressor related noise exceedances in the night period in August 2023, however, did not initiate effective mitigation until November 2023. Gamuda has since had custom silencers fitted to the compressors to reduce noise impacts.

Inspections

16/06/2022

10/11/2022

1/03/2023

10/08/2022

31/08/2022

17/11/2022

16/02/2023

23/03/2023

26/10/2023

6/12/2023

23/01/2024

22/01/2024

16/01/2024

8/02/2024

25/02/2024

21/03/2024

27/03/2024

1/05/2024

3/06/2024

3/06/2024

19/06/2024

1/07/2024

4/07/2024

4/07/2024

24/10/2024

25/10/2024

28/10/2024

Note: Only enforcements and inspections undertaken by the Department from March 2020 will be shown above.

Submissions

Filters
Showing 181 - 188 of 188 submissions
Ausgrid
Comment
Sydney , New South Wales
Message
Attachments
HERITAGE COUNCIL OF NSW
Comment
PARRAMATTA , New South Wales
Message
See attached letter for comments. We can assist with conditions at RTS stage.
Attachments
NSW Health
Comment
St Leonards , New South Wales
Message
Attachments
Strathfield Council
Comment
Strathfield , New South Wales
Message
Attachments
Mayrin Group
Comment
Sydney , New South Wales
Message
Attachments
Parramatta City Council
Comment
Parramatta , New South Wales
Message
Attachments
Heritage NSW - Aboriginal Cultural Heritage
Comment
Wollongong , New South Wales
Message
Attachments
Water Group
Comment
,
Message
Attached.
Attachments

Pagination

Project Details

Application Number
SSI-10038
Assessment Type
State Significant Infrastructure
Development Type
Rail transport facilities
Local Government Areas
Burwood
Decision
Approved
Determination Date
Decider
Minister
Last Modified By
SSI-10038-Mod-6
Last Modified On
06/11/2024

Contact Planner

Name
Keith Ng